October 11th 2019

Phoenix Brickwork have started on site at the new Luton DART

Phoenix Brickwork have secured the masonry and scaffold package and have started on site at the new Luton DART (Direct Air-Rail Transit) for Volkerfitzpatrick / Kier Joint Venture, to form the new Parkway and Central Stations for the automated guided people mover to replace the current shuttle bus service into Luton Airport.
Our package, consisting of internal block walls and worth in the region of £575k with a 17 week build programme started on Monday 23rd September and we are already working closely with VFK Kier on design issues to ensure that the works run as smoothly as possible out on site.
We will update posts as the project progressing and are excited to be involved in such a high profile scheme.